Using the Matrix to Schedule

Created on:
Updated on:

Using the Matrix, you can schedule many weeks at a time and consolidate multiple scheduling requests into one email per person.

Check out this clip from Planning Center University.

Schedule Teams

Load the matrix with the plans that you want to schedule from, and then click the dropdown arrow next to a team to expand the positions.

expand team.png

In the team section, there are four different ways you can schedule people in the matrix.

team_numbered.png
  1. Click and drag the name of the person you wish to schedule to another plan. They will be added to the position, and a notification will be prepared for them.

  2. Hover over an empty position, and click on the schedule a person link when it appears.

  3. Click on the x person(s) needed link to fill a needed position.

  4. Click + person to schedule a person to the team.

drag to schedule.gif

Add Needed Positions

If you need additional needed positions for the plan, hover over the date in the header, and click needed positions.

needed positions.png

Send Emails

To send an email to people who are scheduled in the matrix, click email these people.

email these people_arrow.png

The matrix will compile one email for all people who are scheduled for multiple times.

Notice

If you have someone on a schedule for many dates, they will just receive one email instead of several. They will still respond to each individual date, but it will cut back on the number of emails being sent to their inbox.

respond to requests.png
Was this article helpful?
103 out of 150 found this helpful